FAQs
Where will the new water storage tank be located?
The new tank will be constructed on the site of the existing water reservoirs north of Longs Peak Avenue between Sunset and Hover streets.
What is the planned size and shape of the new water storage tank?
The new tank will be a circular, pre-stressed concrete tank with a domed roof. The crest of the domed roof will be approximately 20 feet higher than the roof line of the existing reservoir cover. It will be partially buried, and will store water above ground, raising the high water line by approximately 21.5 feet.
What will happen to the existing 2MG reservoir?
The existing 2MG reservoir is no longer needed. It will be demolished and then filled in with dirt and covered with grass.
Will a new fence be constructed around the water tank?
Yes, a new fence will be installed around the entire perimeter of the new tank and the existing communications facility (aka water tower). The project will remove the current fence and install a new chain link fence with black PVC coating closer to the new facility.
Will the existing elevated storage tank (aka water tower) be removed?
No, this project will not impact the existing water tower. It is still serving a purpose as a communications tower and is currently in acceptable condition
Will this project limit access to the Sunset Pool and Golf Course Club House?
The Sunset Pool, Sunset Golf Course, and associated parking lots will NOT be closed during construction. There will be limited impacts to the parking lot for replacement of existing water mains, but the selected contractor will be required to maintain access to the adjacent recreation facilities at all times.
Will any trees in the project area be removed?
Yes, a limited number of trees will be removed to allow for water line installation. Existing trees along Longs Peak Avenue and at Price Park will be protected in place. Several new trees and shrubs will be planted around the project site to buffer the facility from the adjacent properties.
Will the xeriscape garden be impacted?
Access to the xeriscape garden and walking path will be restricted during construction. The xeriscape landscaping and path will be restored as part of the project.
Will Longs Peak Avenue be open during construction?
Yes, vehicle traffic will be allowed in both directions at all times. Westbound Longs Peak Avenue, including the sidewalk, will be temporarily closed during construction to allow for construction staging. Eastbound Longs Peak Avenue will be temporarily widened to allow for two-way traffic and pedestrian access during construction. Access to the Sunset Pool and Sunset Golf Course parking lots will be maintained during construction. Westbound Longs Peak Avenue including the sidewalk will be re-opened after construction of the project.
Will pedestrians be able to use the sidewalk along Longs Peak Avenue?
The existing sidewalk along westbound Longs Peak Avenue will be closed during construction between the Sunset Pool parking lot and Price Park. A temporary walkway will be installed along the eastbound lanes of Longs Peak Avenue, including crosswalks and signage, to facilitate east-west pedestrian access. The bottom section of the existing stone stairs will be removed during construction and the stairs will be reinstalled after the work is complete. No other impacts to the stone wall are anticipated.
Will the speed limit be reduced on Longs Peak Avenue during construction?
No, the current posted speed limit is 20 mph. Longs Peak Avenue is a low-volume residential street, which does not require a speed reduction during construction.